Daytime Noise Monitoring Results                    
                           
Station M7, Wah Ming House                      
Date Start Time End Time  Weather Noise level (dB(A)), 30 min Major Construction Noise Source(s) Observed Other Noise Source(s) Observed Remarks Temp. (°C) Wind Speed (m/s) Noise Meter Model / ID Calibrator Model / ID
Leq L10 L90
02-Jul-10 10:07 10:37 Sunny 59 60 57 N.A N.A N.A 30 <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
08-Jul-10 09:04 09:34 Sunny 65 68 61 Grouting works Repaving floor
construction at
Wah Ching House 
N.A 30.6 <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
13-Jul-10 11:03 11:33 Sunny 61 62 59 Operation of hydrulic excavator Repaving floor
construction at
Wah Ching House 
N.A 29.9 <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
20-Jul-10 09:19 09:49 Sunny 63 64 61 Operation of hydrulic excavator N.A N.A 29.5 <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
26-Jul-10 09:32 10:02 Sunny 63 64 60 Operation of hydrulic excavator N.A N.A 29.2 <5 B&K 2238   S/N : 2684502 B&K 4231  S/N: 2385180
      Min.  59                  
      Max. 68